Action Planning
Planning Meeting
Set-up Primer
Graduates of any PPI /
Randolph Craft planning programs:
Click
Here to
reqest your .pdf version of the complete planning primer
In the e-mail request, include your name and which program
you attended.
Operational
Definitions
PLAN (N)
1. a drawing or diagram drawn on a
plane: as
a: top or
horizontal view of an object
b: a
large-scale map of a small area
2. a: method of carrying out
a desigh: DEVICE
b: method
of doing something: PROCEEDURE
c:
detailed program of action
d: GOAL,
aim
3. an orderly arrangement of parts
of an overall design or objective.
syn PLAN, DESIGN, PLOT, SCHEME,
PROJECT mean a method devised for making or doing something
or achieving an end.
PLAN always implies mental formulation and usually
graphic representation:
DESIGN often suggests a particular pattern and some degree
of achieved order or harmony;
PLOT implies a laying out in clearly distinguished sections
with attention to their relations and proportions;
SCHEME stresses calculation of the end in view and may apply
to a plan motivated by craftiness and self-seeking;
PROJECT often stresses imaginative scope and vision
II. (V) PLAN (planned, planning)
1: to
arrange the parts of: DESIGN
2: to
devise or project the realization or achievement of
3: to
have in mind :INTEND
What Plan/Planning
isn't... Budget, scheduling, projections, etc.
If there isn't a diagram or chart of some kind, little or no
planning has taken place.
Purpose:
An ideal which is held as a
direction - non achievable - what is given back - the reason
for being.
Mission:
A specific achievable "end
point" on the way to and in the direction of the purpose,
and an endeavor toward which all goals are
focused.
Goal:
An end toward which effort is
directed - stated in specific accountable and verifiable
terms.
© Advanced
Management & Planning 1995

Planning Meeting: Information Gathering
Procedures
Review and/or create operational definitions of all key
words.
State and have in writing:
Purpose
Mission
Goal / Intended Results
for meeting
Obtain agreement / "buy in" from all meeting participants
for these items.
(Note: The meeting
facilitator does not participate in the meeting in any other
way than facilitation of meeting proceedures - AMP calls
this the dynamic of the
outsider)
1. END ITEMS:
PICTURE SUCCESS OF THIS GOAL AT SOME POINT IN TIME - BE
THERE.
WHAT THINGS REPRESENT THAT SUCCESS?
&emdash;> Visualize & Use NOUNS
(What objects would you use to tell this goal achievement
story on a "show & tell" table?)
2. ACTIVITIES: For each NOUN listed...
FROM THE POINT OF VIEW OF HAVING ACCOMPLISHED THE STATED
GOAL, WHAT DID WE HAVE TO DO TO GET OR HAVE THIS ITEM
(NOUN)?
&emdash;> Visualize the work that was done (past tense)
& Use VERBS
3. TIMELINE INFORMATION: For each VERB listed...
How long did this work take to complete - in hours, days, or
weeks?
[duration - not deadline]
4. $COST: For each VERB listed...
How much did it cost to complete this work ?
5. RESPONSIBILITY: For each VERB listed...
Who was responsible for the completion of this work? Who did
the actual work?
6. RELATIONSHIP: For each VERB listed...
What had to happen before this work can get started? What
happened after it was done?
These can be listed as End Items OR Activities
This information, properly gathered, can be used in the
MAP®
-
MasterTRAX®
Action Planning - network based
graphic documents.
© Advanced Management & Planning 1995

Planning Meeting:
Information Gathering
Procedures

© Advanced Management & Planning
1995
How do I build a project plan?
Successful projects do not just happen, they are
planned.
The Pacific Planning Institute will ensure that you have
a project which is workable, makes best use of limited
resources and is economically feasible. Think of it as a
dress rehearsal where all teething problems, like casting
and organization, are sorted out before the opening
night.
|
Step 1: Break
Down the Project
|
The project is essentially a set of operations
to be completed in a logical order. These
operations take time to and may use resources. You
may start by listing all the operations in your
project. Alternatively, you can use the Work
Breakdown Chart to prepare an outline for the
project. This might consist of the different
objectives of the project, which could be products,
services, cost accounts - in short, work
packages.
|
|
|
|
|
Step 2: Build
the Model
|
Choose a networking technique - The choices are
"Precedence" or "Arrow" using the more
sophisticated of the project management programs
available - then add the operations one at a time
into the model.
At this stage, enter just basic information for
each operation - a description and the estimated
time it will take (its duration). Calendars define
each duration in terms of working and non-working
time.
Initially, do not worry about allocating
resources or even attempt to anticipate any
resource problems - you can deal with these
later.
Gradually build up the model which shows the
operations involved and the order in which they are
performed. If you are working on a large project
then divide the network into more manageable
portions or subprojects.
|
|
|
|
|
Step 3: Timing
the Project
|
After we've entered the durations and the
sequence of logic, we'll carry out a Time Analysis
to find out when each operation could start and
finish. Our planning network then calculates the
shortest time in which the project can be
completed.
In doing so, we identifiy the Critical Path(s)
or chain(s) of operations which take the longest
time to accomplish. The calculated completion date
depends on the critical operations starting and
finishing on time - if they are delayed, the whole
project is delayed.
We also show the operations which could be
delayed without affecting the project as a whole -
these operations have spare time or "float."
The completion date is of course, a theoretical
one. In practice, if you do have more time then you
can extend the project deadline. The reverse
situation usually applies - you will be trying to
make the project finish sooner rather than later.
Accelerate the project by concentrating on the
critical operations - can you reduce their
durations, overlap them or move them onto calendars
with more working time?
Once you have achieved a satisfactory but
realistic completion date...
|
|
|
|
|
Step 4: Allocate
Resources and Costs
|
Enter the resources available to the project
then allocate them to the individual
operations.
When analysing resources, our planning netowrk
makes full use of float to resolve conflicting
resource demands. It does this by delaying
non-critical operations within their float period
so that the resources are released to more urgent
operations. The problems arise when the project as
planned runs out of float
Carry out a Resource Analysis - Deadline
Critical to see if you need more resources for the
project to finish on time and/or a Resource
Analysis - Resource Critical to find out how long
the project will take using the resources you
have.
If you have entered cost information for each
resource, then carry out Resource Analyses (with
Analyse Costs switched on via the Analysis Control
Panel on the Analysis menu) to compare the cost of
overloading resources against the cost of extending
the project deadline.
You can also use network planning's costing
facilities to forecast cash flows, create budgets
and prepare job costings.
Once approved, you are ready to launch your plan
into the real world. At this point, the role of the
network switches from planning the project to
controlling it. Use it to monitor and co-ordinate
the live project.
|
|
|
|
|
Step 5:
Communicating
|
Take full advantage of the array of reports
available to keep the project team fully informed.
This reduces stress on the part of all working on
the project or the jobsite and communicates to all
that "management has it together."
To ensure that the right information reaches the
right people, use the report features available to
design and tailor your own individual reports.
Pacific Planning Institute's on-the-job experience
can help design these reports if you don't know
exactly what you want and need.
Obviously, information needs to flow in two
directions so when the project team reports back to
you...
|
|
|
|
|
Step 6: Tracking
Progress
|
Use feedback from the team members to update the
model periodically. This ensures that you maintain
an accurate picture of what is happening in the
real project.
Some operations will start and finish as
planned, some may even complete early while others
are delayed. These inevitable changes and delays
must be entered into the model which can then be
re-analysed.
Compare the revised schedule with the original
forecast to pinpoint slippage. Review all possible
lines of action and amend the model accordingly.
Compare actual costs against budgets and earned
values to keep control of project spending. Issue
new schedules to start the whole process over
again.
|
|
|
|
Copyright © 1999 Pacific
Planning Institute / Randolph Craft. All rights
reserved.
|
Top of Page